Temporary works audit checklist

For auditing BS 5975-style procedural control on a live project. Professional design questions belong to your TWC and designers.

  1. Is a designated individual appointed at organisation level with documented arrangements?
  2. Is a TWC appointed in writing for this project, with authority and time to do the role?
  3. Does the register capture every temporary works item on site today — walk it and compare?
  4. Does every item have a design brief before design, and a design before erection?
  5. Are design checks at the right category, by checkers with the required independence?
  6. Are permits controlling the hold points: proceed, load, unload/strike?
  7. Do site conditions match the design assumptions — supports, ground, loads, sequence?
  8. Are alterations to temporary works going back through design, not improvised?
  9. Are inspections happening at the frequency the design or standard requires, with records?
  10. Do the operatives erecting and striking know the sequence and its limits?

This checklist is a starting point prepared by Temporary Works Consulting & Design Ltd. It is not a substitute for the standard, for legislation, or for competent advice, and completing it does not make an organisation compliant or certified. A competent person must adapt it to your organisation before reliance.